We’ve been having lots of trouble getting the company who installed our solar panels to turn in the correct paperwork to Burbank Water & Power.

This paperwork is needed before we can get our inspection.

We need to pass inspection before we can see the correct power consumption on our electric bill.

We also can’t get our rebate until the paperwork is done. It’s a large rebate.

We aren’t happy.

Here’s what we’ve learned a little too late: If you pay the company doing your solar the full amount, they don’t have much motivation to process paperwork. If you hold back the amount of the rebate check, they turn things in quickly.

So now we know.

You can follow any responses to this entry through the RSS 2.0 feed. You can leave a response, or trackback from your own site.

Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>